1.      General Information of the Project:

·      Name of Project                :           IWMP Aizawl-XXI, 2013/2014
·         Location of Project           :           Phullen RD Block, Aizawl District. Mizoram.
·         Project Cost                      :           Rs. 630 Lakhs
·         Project Area                      :           4200 Ha.
·         Name of PIA                    :           All Mizoram Farmers’ Union (AMFU)


2.      Entry Point Activities (EPA):

a.      Construction of Market Shed cum YMA Library:

                                         i.         Dimension (Size)                             
1.      Market Shed               :  Breadth 12 ft x Length 15 ft x Height 9 ft
2.      Library                        :  Breadth 12 ft x Length 15 ft x Height 10 ft
                                       ii.         Location                                           :  Lamherh
                                     iii.         Date of start construction work         :  17.03.2014
                                     iv.         Date of Completion of Work           :  31.07.2014



b.      Construction of Public Water Tank (Vaituikhur) & Approach Road:


                                         i.         Dimension (Size)
1.      Public Water Tank                  :           12 ft x 10 ft x 3 ft
2.      Water Tank Approach Road   :           380 m x 3 m
                                       ii.         Location                                           :           Vanbawng
                                     iii.         Date of start construction work       :           15.04.2014
                                     iv.         Date of Completion of Work           :           18.07.2014







c.       Construction of Community Hall Approach Road (RCC):

                                         i.         Dimension (Size)                              :           112 m x 3 m
                                       ii.         Location                                           :           N. Khawlek
                                     iii.         Date of start construction work       :           13.05.2014

                                     iv.         Date of Completion of Work           :           03.07.2014