ENTRY POINT ACTIVITIES (EPA) UNDER IWMP AIZAWL-XXI
REPORT
ON ENTRY POINT ACTIVITIES (EPA) UNDER IWMP AIZAWL-XXI
1. General
Information of the Project:
· Name
of Project : IWMP Aizawl-XXI, 2013/2014
·
Location of Project : Phullen
RD Block, Aizawl District. Mizoram.
·
Project Cost : Rs.
630 Lakhs
·
Project Area : 4200
Ha.
·
Name of PIA : All
Mizoram Farmers’ Union (AMFU)
2. Entry Point
Activities (EPA):
a.
Construction
of Market Shed cum YMA Library:
i.
Dimension (Size)
1.
Market Shed : Breadth 12 ft
x Length 15 ft x Height 9 ft
2.
Library :
Breadth 12 ft x Length 15 ft x Height 10 ft
ii.
Location : Lamherh
iii.
Date of start construction work : 17.03.2014
iv.
Date of Completion of Work :
31.07.2014
b.
Construction
of Public Water Tank (Vaituikhur) & Approach Road:
i.
Dimension (Size)
1.
Public Water Tank : 12 ft x 10 ft x 3 ft
2.
Water Tank Approach Road : 380
m x 3 m
ii.
Location : Vanbawng
iii.
Date of start construction work : 15.04.2014
iv.
Date of Completion of Work : 18.07.2014
c.
Construction
of Community Hall Approach Road (RCC):
i.
Dimension (Size) : 112 m x 3 m
ii.
Location : N. Khawlek
iii.
Date of start construction work : 13.05.2014
iv.
Date of Completion of Work : 03.07.2014